Major Completed Projects

Water Proofing Work

Roof Water proofing system in Substation #1, 9, 16 and Plant 476 OME Building.
Client Name: Saudi Aramco, Location:Berri Gas Plant, Jubail.



Concrete Pipe Supports Repair

Perform Civil and Mechanical Work @ RTR Plt #151 Area 4.
Client Name: Saudi Aramco, Location:Rastanurah Refinery.



Excavate Trench Work

Excavate Trench to Run Spare Control and Signal Cables.
Client Name: Saudi Aramco, Location:Ju’aymah Gas Plant.



Maintenance Work

Replacement of Underground Water Asbestos Pipes 250mm (OD) at Doha.
Client Name: Saudi Aramco, Location:Doha



Replace 6 Chilled Water Pumps & One Cooling Water Pumps

Replace 6 Chilled Water Pumps



Increase Pressure & Flow of Raw Water System @ Qurrayah

Complete 100% 



Replace SCUM Pump G5 & Return Sludge Pump G3 at STP

Complete 100% 



Revovation Of Engineering Building Coffee Room

Complete 100% 



Replace Effluent Return Pump- B ( M64-G-057B) In Hida Pumping

Complete 100%



Industrial Electrical Works

Complete 100%



Revovation Of Engineering Building Coffee Room

Complete 100%



Increase Pressure & Flow of Raw Water System @ Qurrayah

We Complete project on 12/15/2018



Replace SCUM Pump G5 & Return Sludge Pump G3 at STP

We complete the Project on 07/31/2018.



Revovation Of Engineering Building Coffee Room

We Complete project on 02/28/2019



Replace 6 Chilled Water Pumps & One Cooling Water Pump at

We Completed Project On 01/27/2019



Replace Effluent Return Pump- B ( M64-G-057B) In Hida Pumping

We Completed Project On 11/27/2018 (100%)



Replace Five (5) Pumps at AC Plant No. 2, Abqaiq

We Completed Work on 1/22/2020 ( 100%)



Install Backup Power Supply- For Shedgum Drilling Work

We Completed work on 10/31/2019 ( 100%)



RTR HR Building Renovation

We completed 100%